Project background
This home sits in Cordillera, Edwards’ gated luxury mountain community, where exterior finishes are expected to look and perform at the highest level. The scope was a full tear-off of the existing wood shake roof and a complete redeck of the roof surface.
The redeck was required because of how the home’s overhangs are finished. At the eaves and the rakes, the roof deck itself is the finished decorative soffit. The paneling you see from outside looking up at the overhang (which reads as tongue-and-groove but is actually a single panel) is also the material the roof is built on.
The DaVinci Select Shake system requires nails to penetrate the roof deck per manufacturer specification, which in those overhang areas would mean driving nail points through the finished decorative soffit. To preserve the finished look of the decorative soffits and keep the DaVinci manufacturer warranty intact, we installed new sheathing on top of the existing deck across the entire roof. The new sheathing gave the DaVinci system a clean nailing surface above the decorative soffit layer and allowed us to nail through the roof deck exactly as DaVinci’s installation spec requires. Skipping that step would have voided the manufacturer warranty.
The project also included full gutter and downspout replacement, a new snow retention system, and a full remove-and-replace of the heat cable system.
Roof replacement details and cost
Roof size: 57 squares, approximately 5,700 sq ft
Roof system total: $136,142.00 (includes $6,655 redeck)
Cost per roofing square: approximately $2,388
Cost per square foot: approximately $23.88
Material removed:
• Original wood shake roofing
Redeck: New sheathing installed over the entire existing roof deck. See the Project background section above for why this was required.
Redeck cost: $6,655.00 (included in the roof system total above)
Material installed: DaVinci Select Shake composite shake, color Black Oak
Exposure: 10-inch exposure
Fire rating: Class A fire-rated roof assembly
Underlayment: Flash Deck Metal Base high-temp ice and water shield across the entire roof deck, with EcoChief Solarhide installed over the top to complete the Class A fire-rated assembly
Flashing: All metals were custom-made in heavy 24-gauge, including custom double-diverter valley flashings. The double diverters give the valleys clean lines and cover the cut edges of the DaVinci shake. The heavier gauge also adds extra snow load support and ice dam protection.
Fasteners: Hot-dipped galvanized ring-shank nails per DaVinci specification, to meet manufacturer wind warranty requirements and eliminate the long-term risk of nails rusting out
Pipe boots: All pipe boots removed and replaced
Manufacturer warranty: Standard DaVinci Select Shake lifetime limited material warranty (with 10-year non-prorated period)
Workmanship warranty: 10-Year Pak Exteriors Workmanship Warranty
Ventilation
Ventilation scope: The home’s existing intake ventilation was already adequate, so no intake changes were needed. The only adjustment was a slight reduction in exhaust at the ridge vent to balance the intake-to-exhaust ratio correctly for the new DaVinci Select Shake system.
Ember blocking: Ember blocking screens were installed at the attic openings where the ridge vent is located. This is required under the 2026 wildfire codes to prevent wind-driven embers from entering the attic through the ridge vent during a wildfire event.
Gutters and downspouts
Scope: Full replacement of all existing gutters and downspouts
Gutter quantity:
• 262 linear feet of gutters
• 144 linear feet of downspouts
• 406 linear feet total
Gutter guards: 262 linear feet (covering the full gutter run)
Gutter system components:
• 12 gutter elbows
• 14 gutter end caps
• 18 gutter miters
• 12 gutter outlets
Gutter system total: $10,440.00
Snow retention system
Scope: New snow guard system installed to protect the entry areas, walkways, and gutter system from sliding snow and ice
Snow retention total: $14,409.00
Heat cable system
Scope: Existing heat cable system removed and replaced with new heat cable
Heat cable quantity: 160 linear feet
Installation, permits, and inspections
Installation duration:
• Material staging: 1 day
• Roof redeck, snow guard installation, and heat cable replacement: 6 days
• Gutters and gutter guards: 1 day
Permits: Eagle County
Inspections completed:
• Roof final inspection (No mid-roof inspection required)
Permit status: Permit passed and finaled